Lundin Mining begins production at $400m Eagle project in Michigan

Note* - All images used are for editorial and illustrative purposes only and may not originate from the original news provider or associated company.

Subscribe

- Never miss a story with notifications

- Gain full access to our premium content

- Browse free from any location or device.

Media Packs

Expand Your Reach With Our Customized Solutions Empowering Your Campaigns To Maximize Your Reach & Drive Real Results!

– Access the Media Pack Now

– Book a Conference Call

– Leave Message for Us to Get Back

Related stories

Apple Invests $500mn in MP Materials to expand U.S. supply

In a recent move, technology giant Apple Invests $500mn...

Egypt and Saudi Arabia Exploring Mining Cooperation Options

The Egyptian minister of petroleum and mineral resources, Karem...

Steel Tariffs To Protect Domestic Steel Industry In Canada

Prime Minister Mark Carney of Canada on July 16,...

New Mining Law in Egypt to Shift EMRA Into Economic Entity

A new amendment to the mineral resources law in...

Canada-based Lundin Mining has started commercial production at its $400m Eagle nickel-copper mine in Michigan, US.

 

The company announced that construction activities are now complete and the project has been delivered on-budget and ahead of schedule.

 

Lundin Mining president and CEO Paul Conibear said: “We are extremely proud of the tremendous achievement that has been accomplished at the Eagle Mine.

 

“The Eagle Mine is a significant new, high-quality, low-cost mine, that has been constructed to the highest of safety, environmental and social responsibility standards.

 

“Our team has done an exemplary job in bringing the mine into production and we look forward to the operation becoming a significant cashflow generator for the company and a significant contributor to the local and regional economy.”

 

The company expects Eagle mine to produce an average of around 23,000t of nickel concentrate a year and around 20,000t of copper concentrate a year over the first three years of operation.

 

Lundin plans to ship the first saleable copper and nickel concentrates from the mine during the first half of October this year and is expected to reach full design rates in the second quarter of 2015.

 

The mine’s current truck hauling rate is approximately 1,500t of ore a day from mine to the mill. It is further upgrading the roads to enable full production rate ore hauling.

 

Lundin is also in the process of shipping the saleable nickel and copper concentrates by rail, which is expected to occur in the first half of this October.

Latest stories

Related stories

Apple Invests $500mn in MP Materials to expand U.S. supply

In a recent move, technology giant Apple Invests $500mn...

Egypt and Saudi Arabia Exploring Mining Cooperation Options

The Egyptian minister of petroleum and mineral resources, Karem...

Steel Tariffs To Protect Domestic Steel Industry In Canada

Prime Minister Mark Carney of Canada on July 16,...

New Mining Law in Egypt to Shift EMRA Into Economic Entity

A new amendment to the mineral resources law in...

Subscribe

- Never miss a story with notifications

- Gain full access to our premium content

- Browse free from any location or device.

Media Packs

Expand Your Reach With Our Customized Solutions Empowering Your Campaigns To Maximize Your Reach & Drive Real Results!

– Access the Media Pack Now

– Book a Conference Call

– Leave Message for Us to Get Back